Update on the Cheviot Mine
December 1, 2002
Wild Lands Advocate update, December 2002, by Philip Clement.
Cardinal River Coals is keeping us updated on the progress of their application for a new private haulroad. Their newsletter explains that they submitted an application for an amendment to the Cheviot Mine permit and the environmental approval for the Luscar mine to seek regulatory approval to construct a 10 km private haulroad to link the two mine sites.
Read the complete update: 200212_AR_CD.pdf