Personal tools
You are here: Home Issues Wildlands Areas of Concern Cardinal Divide History
 

History

Cardinal Divide History

Date Event
June 2005 June 14: Federal Case for Cheviot Mine (Edmonton).
May 2005 The Federal case hearing against the Cheviot Mine will occur the week of May 23, 2005 at the Federal Court in Edmonton.
April 2005 April 13: Minister of Environment, Guy Boutilier, releases his decision on the Bed Gadd hearing. Recommendations put before the Minister in February by the Alberta Environmental Appeals Board were approved by the Minister. Although the board agreed the road would negatively affect Ben Gadd, they determined that the road would have environmental benefits compared to the original project. Therefore, the Cheviot haul road would not be closed, however the company must make some changes to their operations. Among these changes are:
  • No salt is to be used on the haul road because it attracts wildlife to the road
  • Wildlife killed by the mine must be reported immediately
March 2005 Mar. 29: SLDF recommends that the issues on the litigation be split, i.e. proceed with the Federal Case against DFO and leave the CRC constitutional case for a later date – yet to be determined.
February 2005 Feb. 8: Counsel for CRC notifies SLDF that they are serving a notice of constitutional question challenging part of the Migratory Bird Convention Act. ENGOs had put the applicability of that Act at issue arguing that the CRC’s rock dumps are illegal. This attack on the constitutional validity of the Migratory Bird Act could change the nature of the litigation.

Feb. 24: Alberta Environmental Appeals Board provides the Environment Minster, Guy Boutilier, their report on the outcome of Ben Gadd’s hearing. Decision are generally made within 30 days.

November 2004 Nov. 4: The Court of Queen's Bench rules that Ben Gadd has the right to appeal approvals for the Cheviot haul road. The case is scheduled to be heard January 24 and 25, 2005 and is open to public viewing only.

Nov. 3: Cardinal River’s Coal’s case against the Alberta Environmental Appeals Board decision is heard to determine whether to allow the Ben Gadd hearing.

Nov. 2: Conservation groups launch another legal challenge against the Federal Governments recent authorizations of the Cheviot Creek Development (first phase of mine development). The groups challenge the authorization should be quashed because it directly contravenes the Migratory Bird Convention Act.

October 2004 Oct. 12: The Department of Fisheries and Oceans notifies conservation coalition that they have granted an Authorization for first phase of the Cheviot project; the Cheviot Creek development. The authorization was issues September 20, 2004.
September 2004 Sept. 27-28: Alberta Environmental Appeal Board was to have heard Ben Gadd Cheviot haul road appeal in Hinton.

Sept. 20: Alberta Environmental Appeals Board delays Ben Gadd’s appeal hearing for five weeks at the request of Cardinal River Coal Ltd.

Sept. 17: Cardinal River Coal serves notice that it has applied to the Court of Queens Bench of Alberta for a judicial review of Alberta Environmental Appeals Board’s decision to proceed with Ben Gadd’s appeal of the haul road development and modified Cheviot project.

Sept 10: The Alberta Environment Appeals Board denies Teck Cominco’s and Fording’s request to delay Gadd appeal hearing of the Cheviot coal mine haul road.

Offer by coalition to expedite Gadd case turned down by companies.

Sept. 1: Coalition and Sierra Legal Defense Fund, made a joint offer to Cardinal River Coal to expedite its federal case and stay Ben Gadd’s appeal of his proceedings if CRC and its parent companies agreed to stop all work on Cheviot haul road (Sept. 1).

Sept. 1: Cardinal River Coals and its parent companies Teck Cominco and Fording Canadian Coal request a stay in the appeal hearing of Ben Gadd to appeal the haul road (Sept 1).

August 2004 ENGOs hold a press Conference in Edmonton regarding legal action taken by ENGOs against DFO regarding the Cheviot Project.

A Notice of Application is filed by Sierra Legal Defence Fund on behalf of AWA, CNF, Pembina and Sierra Club Canada and Jasper Environmental Association. They serve DFO Prairie Office and Elk Valley Coal in regards to new haul road development for Cheviot Mine.

The Federal appeal was filed by conservation coalition calling for an environmental assessment of the entire Cheviot coal mine project. A Notice of application for judicial review was filed of the failure of the Minister of DFO to comply with his duties under CEAA in relation to the cheviot Mine Project. The Minster failed to comply with his duty under CEAA to prepare an environmental assessment of modifications for the Project before exercising power that would enable the mine project to be carried out in whole or in parts.

June 2004 June 28: SLDF has determined there is a course for legal action regarding the Fisheries Act and the Cheviot Mine.
  • Application to be made for a judicial review of the failure of the Minster of Fisheries and Oceans to comply with his duties under CEAA in relation to the Cheviot Coal Mine Project. The Minister failed to comply with duties under CEAA to prepare an EIA of the modifications on the new project before issuing authorizations.
  • DFO has a duty under CEAA to implement the mitigation strategies identified in the Joint Panel and Federal reports of 1997 and 2000. DFO is not intervening as Elk Valley Coal proceeds with the construction of the haul road in the absence of authorizations.
  • DFO must continue to assess the modified project and implement appropriate mitigation measures. DFO is the lead responsible authority under CEAA responsible for the assessment and mitigation of the previously assessed Cheviot mine.
  • Authorizations have expired and DFO has failed to require EVC to reapply for authorizations and in doing so is ignoring project modifications.
  • There are further environmental impacts associated with the new project including greater impacts on Jasper National Park, grizzly bears, migratory birds and habitat, and fish and fish habitat.
May 2004 May 26: The Alberta Environment Appeals Board grants Ben Gadd standing at Cheviot Haul road Appeals hearing, still to be announced. Gadd has obtained legal standing because he runs an ecotourism operation in the valley.
April 2004  April 26: Ben Gadd appeals to Alberta Environmental Appeals Board that Cheviot will impact his ecotourism business. He appeals the provincial permits issued in December 2003 for the haulroad. Gadd formally asks the company halt construction of the haulroad until a decision is rendered on his appeal but they refuse.

April 21: AWA Coalition representatives hold a press conference in Edmonton regarding Ben Gadd’s appeal of Cheviot Haul Road.

April 12 - 13, 2004 The AWA coalition via Sierra Legal Defence Fund (SLDF) sends a letter to Honourable Geoff Regan, DFO (Ottawa) and Honourable David Anderson, Minister of Environment, to refer the haul road project to be part of a full EIA under CEAA. SRD and the Superintendent of Jasper National Park also ask Alberta Environment for an EIA. As an argument, the groups highlight the Elk Valley Coal report prepared by their consultant on aquatic resources. The consultant recognizes the potential significant impacts that the new haulroad will have on fish and fish habitat and that these impacts are substantially different than those previously assessed in 1997. The report indicates that the haulroad could result in habitat losses or alterations. Particularly, the report noted the loss or disturbance of fish habitat at stream crossings and channel intrusions.

The groups also identify that there are several instream works that are part of the new haulroad project that would require federal authorisations under the Fisheries Act. These new instream works include the installation of culverts and a water management structure.

Furthermore, most of the issues addressed in the 1998 federal authorization remain relevant but have not been adequately addressed in regards to the new project. The federal government must become engaged in the issue to ensure the environmental impacts of the new project are assessed under CEAA. There are no federal authorizations in place for the Cheviot project but Elk Valley Coal has begun developing the road. CRC has not received authorization under the Fisheries Act for any of these activities which are part of the new proposal and an assessment must be done prior to getting such approval.

March 16, 2004 Fording Canadian Coal Trust announces that the Elk Valley Coal Partnership will proceed with the development of the Cheviot Creek pit at its Cardinal River Operations due to improved export sales. The cost of the project will be approximately $50 million dollars and have an annual production rate of 1.4 million tonnes

Elk valley Coal submitts a mine license application for the final approval to AEUB and AENV.
December 2003  AENV grants permits for the Cheviot mine haulroad. The company no longer has federal authorization for Cheviot, but by planning the new satellite mine project and parcelling it into individual projects, such as the haulroad, the company receives provincial permits and circumvents the required federal authorizations. They have broken the new mine project into various separate activities, applying for one piece at a time so that a review of the entire project is not triggered.
April 2003 The EUB issues an enlarged mine permit for the new Cheviot project. Neither the provincial nor federal governments require any EIA.

Fording Coal Partnership says it will not be developing the Cheviot mine. Cheviot is shelved until prices and the demand for coal improve. ENGOs are once again pleased, but point out the economic instability of the Cheviot Mine development.
March 2003 March 1: Fording Canadian Coal Trust takes possession of Luscar and Cheviot properties in a swap of assets with Luscar Coal. Luscar and Consol merge with Fording River Coal. The Fording Canadian Coal Trust announces that Elk Valley Coal (EVC) will proceed with the development of the Cheviot mine.
February 2003 Feb. 28: Fording is converted into the Fording Canadian Coal Trust - a multi-party agreement among Fording Inc., Teck Cominco Limited, Westshore Terminals Income Fund and Sherritt Coal Partnership II, a partnership of Sherritt International Corporation and Ontario Teachers’ Pension Plan. The transaction combines the metallurgical coal assets of Fording Inc., Teck Cominco Limited and the Luscar/CONSOL Joint Ventures. The Elk Valley Coal Partnership is also created through a merger of Fording Inc., Luscar Limited and Teck Cominco Limited. It is the world’s second largest producer of export metallurgical coal.

Teck Cominco became part of Cheviot holdings (35% owner of Cheviot) with Fording Canadian Coal (65% owner).

December 2002 The AEUB requests a revised EIA from CRC. The CRC is to provide information on all potential and cumulative environmental effects of their revised proposal for the Cheviot coal mine and not just the haulroad.
October 22, 2002 The AWA Coalition is reformed with nine other organizations and individuals (JEA, Ben Gadd, Pembina Institute, AWA, Toxic Watch Society, CPAWS, CNF, Mining Watch Canada, Sierra Club, Environmental Resource Centre of Canada). The coalition writes to the Federal Environment Minster, David Anderson, to request that DFO and the Prairies Area Office of DFO conduct a thorough EIA of the impacts of the haul road and the entire satellite mine on fish and fish habitat of the McLeod River system under the CEAA. The coalition argues that:
  • This new Cheviot Mine project is so fundamentally changed that it now constitutes a new project. It must be reviewed in accordance with CEAA and new public hearings should be held. Any approvals from DFO should not be granted until the new project has been assessed through a review panel. CRC did not proceed with the mine project after the assessment was completed. Instead they proposed a modified version. The manner in which the project is to be carried out has changed. These circumstances require the Responsible Authority, the Minister of DFO, to undertake an EIA. He must make adjustments to the existing EIA report to account for the significant changes in the environment brought about by the new project. These obligations can only be met by conducting a new review on the entire new project.
  • The proposed private haulroad itself triggers a Fisheries Act review under CEAA which requires a full review under CEAA. The impacts of construction and operation of this high speed road were not assessed through detailed environmental review in 1997. The Alberta government gave Elk Valley Coal the go ahead for this road based on an EIA done on the original project for a railway up the valley
  • CEAA provides that a project includes any proposed construction, operation, modification, decommissioning, abandonment or other undertaking in relation to physical work. Once CEAA has been triggered, the Act requires that an EIA be conducted in respect to every construction, modification, decommissioning abandonment or other undertaking in relation.
  • Under CEAA Section 24:
    24.(1) Where a proponent proposes to carry out in whole in part, a project for which a EIA was previously conducted and;
    a) the project did not process after the assessment was completed;
    b) in the case of a project that is in relation to a physical work, the proponent proposes an undertaking in relation to that work different from that proposed when the assessment was conducted;
    c) the manner in which the project is to be carried out has substantially changed; or
    d) the renewal of a license, approval or other action under a prescribed provision is sought.
    The Responsible Authority shall use that assessment and the report thereon to whatever extent appropriate for the purpose of complying with Sections 18 or 21. Section 24 therefore serves to essentially reengage CEAA and a new EIA.
  • This implies that a new project was conducted and now DFO as the Responsible Authority must undertake an EIA according to CEAA.
  • The 1997 mine application ruled out the development of a satellite mine because of environmental, technical and social reason, CEAA therefore did not address the satellite mine alternative now proposed. The social and environmental reasons given by CRC not to proceed with the satellite mine development included:
    • 1) “remaining mining activities at Luscar mine will not provide sufficient space for the in-pit disposal of tailings for the 20 year life of the Cheviot Mine,
    • 2) “ the animal mortality and significant surface disturbances associated with high speed truck haulage has major environmental implications, and
    • 3) “Physically, there is not enough room within certain segments of the McLeod Rover Corridor to accommodate a private haulage road within a minimum of 30 metres and the necessity for run away lanes, a power line right of way and the existing Grave Flats road.” (CRC 1996). All these impact remain will current mine application and must be examined.
  • There is also a necessity for a new cumulative impacts assessment. The panel did not review the cumulative impacts of operating Cheviot with the continued activity at the Luscar Mine. The change in status of the Luscar mine is a significant change that may effect validity of panel conclusions regarding cumulative effects. The groups reject the CRC's characterization of the construction of the private haulroad as an independent project. It forms part of a larger satellite mine project which will require a number of Fisheries Act permits which should be assessed as a whole and not after preliminary components have been built.
  • The new project is found to be even more intrusive on wildlife, the hamlet of Cadomin, the Whitehorse Creek Wildland Park, and Jasper National Park than the original project.
    • The new gravel haulroad could pose significant problems for wildlife by increasing mortality rates and impeded movement.
    • The road may cause a greater barrier to wildlife movement and ready access for poachers into McLeod valley.
    • The public and haul roads will be side by side and separated by a one-2 metre high concrete barrier, which would impede wildlife movement.
    • The haul road serves as a 22 km north south barrier to wildlife movement. Add this to the 23 km west-east trending mining area.
    • The continuous 24 hour a day, high speed traffic will result in increased road kill and serves as a barrier to seasonal movement. Add this to the quality habitat removed from the area.
    • The road’s adjacency to McLeod river and its tributaries will affect both fisheries and migratory bird habitat including harlequin ducks.
    • Road adjacency and use will result in increased load of sediment and dust and declining water quality for both fisheries and bird habitat.
    • CRC is required as a condition of the mine permit to study current wildlife movement patterns and to establish the minimum conditions necessary for wildlife corridors to be affective. These studies would include the assessment of wildlife use of the McLeod River valley for habitat and movement. This must be done as part of the CEAA review.
  • The changes to the new project reduce the economic and social benefits of the mine. The company will be mining less than half the coal originally sited in 1997, 2.1 M tonnes compared to 3.25M tonnes annually, and employ only one quarter of the people of the original project The review panel in the 2000 decision recommended approval because it felt the economic benefits of the mine would outweigh the environmental and social costs of the project. However, the changes to the project have altered the forecasted costs – the mine will be producing less coal and will require fewer jobs.

Summary of the changes to the project from 1997 to 2000:

  • Access Corridor:
    • 1997
      - Upgrade Grave Flats road (existing road) for access
      - Construct railway
    • 2000
      - Addition of McLeod River Valley to the mine permit to operate Cheviot as a satellite of Luscar
      - Construction and operation of a 22km high speed haul road for round the clock transport of raw coal to Luscar. Haul road to parallel Grave Flats road and McLeod River
  • Transmission Line installation
    • 1997
      - Transmission Line installation
    • 2000
      - New location to parallel haul road and Grave Flats road
  • Coal processing Plant and operation
    • 1997
      - Construction and operation of a new plant at cheviot
    • 2000
      - Use of 40 year old plant at Luscar instead of previously planned shut down and reclamation
  • Surface Mine Development
    • 1997
      - 64 M CMT of coal
    • 2000
      - Plan to mine less than half the amount of coal - 28M CMT.
      - Total area of the mine to remain the same but with a different sequence in opening the pits.
October 3, 2002 A 3 year study by federal and provincial agencies finds that high selenium levels downstream from the Luscar mine are causing deformities in trout.
August 15, 2002 CRC files an amendment application with the EUB and Alberta Environment (AENV) for a new Cheviot Mine development. The amendments to the project are:
  • The Cheviot Mine is to become a satellite mine operation of the existing Luscar Mine. The Cheviot Mine will no longer be a self contained mine, rather all coal will be shipped and processed off site at the existing Luscar Mine 22 km to the north, which was originally slated for closure and reclamation in 2003.
  • The new project will involve the construction of a new 22 km long 70km/hour high-speed coal haulroad adjacent to the McLeod River. This will require the enlargement of the total mine site by adding 10km of McLeod River Valley. In doing so, a 10km section of road will be constructed within the valley to link the satellite Cheviot mine permit area with the Luscar mine permit. The new size of mine area will be 7,455ha.
  • Because the coal will not be processed at the Cheviot site, this eliminates the need to build a rail line and processing plant.
  • The project will not be cheaper to operate and construct because the coal will be hauled off site.
  • The only infrastructure at the Cheviot Mine site will be mobile trailers since Luscar infrastructure will be used.
  • Coal hauling will occur 24 hours a day, 7 days a week. A truck will pass any given point every 6-15 minutes.
  • Seasonal public access will occur along the existing Grave Flats road. Modifications will be made to this road to accommodate the private haul road.
  • The public and private haul roads will be kept separate for safety reasons. The haulroad and Grave Flats road will intersect at three points at marked crossings.
  • The new Luscar mine 69kv power system will be extended beside the haulroad.
July 2002 Luscar changes its plans for the Cheviot Mine and applies for permits for its approval. Luscar plans to build a new haul road from the Cheviot Mine site to the current Luscar mine rather than build a processing plant on site.

CRC submits an application to the Alberta Government for an amendment to the existing Cheviot mine permit and seeks the environmental approval for the operation of the Luscar mine. This is another new development as the Luscar mine was to have closed in 2002. The amendment is to seek regulatory approval to construct a 10km private haulroad to link the proposed Cheviot mine permit area with the existing Luscar mine permit area. Aspects of this proposed haul road include:

  • The road will be a 22 km long private high-speed coal haulroad adjacent to McLeod River, constructed beside the existing Grave Flats road. It would require the development of a new 10km section. 
  • The road will fall within the access corridor that was considered and approved as part of original mine project.
  • The road will be a single lane gravel road about 16 m wide. When topography allows, the road will be extended to a double lane gravel road approximately 30 m wide.
  • The road will proceed after being granted after government approvals.
May 2002 CRC contacts Alberta Environment (AENV) to determine if the Cheviot Mine EIA conducted in 1999 will adequately address the environmental considerations associated with the construction of a private haul road corridor for the Cheviot Mine and if any further study was required. According to the original mine application in 1997, there were only to be upgrades to an existing road. The Minster of Alberta Environment, Lorne Taylor, responds that an EIA report is not necessary. He does not direct CRC to submit an EIA saying “the proposal described is not a mandatory activity requiring an EIA…further assessment of the activity is not required.”
May 2001 Sherrit International and Ontario Teacher's Pension Plan buy out Luscar.
April 2001 The Federal Government accepts the hearing panel recommendation to approve the mine clearing the way for the Federal Government to release regulatory approval.

The Cheviot Mine is still approved, but is on hold until Luscar can secure contracts for coal purchase when market ever returns.  In the meantime Luscar and Consolidated Coal are developing the Line Creek Mine in BC to serve the same market.

March 2001 Sherrit Coal Partnership (including Ontario Teachers Pension Plan) puts in bid on Luscar.

March 26 - The EUB responds to the AWA Coalition’s request for a review of the decision, however the review is denied. The EUB states that CRC postponed the project and did not cancel it.

March 31 - The Luscar Mine closes. The Luscar Mine was opened in 1960. It is located 22km north of the proposed Cheviot Mine Site. Just when Albertans thought that all was quiet on the Cheviot front, the project is resurrected in a different form.

December 2000 Despite the announced postponement of the Cheviot Mine development, the Provincial Cabinet authorizes the EUB to grant a mine permit to CRC for Cheviot. CRC receives federal and provincial approvals for the Cheviot Mine development.
November 2000 The AWA Coalition requests another review of the mine approval. The decision to “shelve” Cheviot constitutes new information which should cause the Panel to reconsider its earlier decision to approve the mine development. The coalition argues that the announcement to delay the project means it is no longer in the public interest and does not comply with CEAA because it is no longer a project. The project has now proven itself to be economically unviable.
October 24, 2000 Luscar announces that the Cheviot Coal Mine Project is postponed and it will close its Luscar mine, in the same region. The Cheviot development is found to be too costly to be viable as operating costs are high and international coal prices remain low. The Japanese did not renew their commitment (withdrew letter of intent) to purchase about 75% of the Cheviot Mine coal. There is no market for Cheviot coal. The Pacific Rim market for metallurgical coal is weak due to a world oversupply and price reduction. Cheviot would be competing for business with mines in Australia. The AWA Coalition is very pleased and believes the Cheviot Mine is officially dead.
September 12, 2000 The supplemental review report of the Joint Review Panel is released. The report recommends the approval of the Cheviot Mine. The decision still requires regulatory approval from the Federal Government of Canada. The conclusions cite potential environmental impacts from the mine development such as significant adverse environmental effects on terrain, soils, migratory birds, harlequin ducks, and grizzly bears, as well as Aboriginal peoples’ traditional use and fish and fish habitat. The report states that mitigation of these impacts is possible.

Further approval of the Cheviot Mine given by the Joint Panel Decision is based on the following (among others reasons):

  • The mine is economically viable and provides significant economic benefit to the region and the province.
  • CRC has adequately considered alternative methods of extraction.
  • Although the proposed mine will have direct affect on water flow rates and water quality both within and beyond boundaries, the environmental effects will not be significant.
  • CRC must avoid or minimize the loss of fish habitat. CRC's planned compensation for fish habitat through the creation of artificial lakes within mine pits is reasonable.
  • With respect to noise and atmospheric emissions, adverse environmental effects will not be significant.
May 2000 Luscar Ltd. closes its Gregg River Mine due to low international coal prices and high operating costs. The Gregg Lake mine is located approximately 20 km from the proposed Cheviot Mine site. This closure reaffirms the economic instability of the coal mining industry and the viability of the Cheviot mine.

May 2 - The Federal Court issues an order formally preventing CRC from acting on the second of the two authorizations it had received for commencement of the Cheviot mine development, i.e. the industrial complex.

March 2000 March 1: A new public hearing regarding supplemental environmental review of mine application is held with the original Joint Panel. This supplemental review is the result of the successful lawsuit launched in October 1997 by the AWA Coalition and Canadian Natural Federation (CNF). AWA presents a joint submission with the AWA Coalition. The hearing is expected to last 15 days in Hinton.

Mine site tiny compared to Jasper Park, Cheviot official says: ‘Ludicrous’ to say mine threat to park. (Edmonton Journal)

March 4: Panel rules alternative mine sites already investigated: Environmentalists criticize review for ‘blocking’ issue (Edmonton Journal)
February 2000 Feb. 17: The Federal Court of Appeal dismisses CRC’s appeal of the 1999 Federal ruling, which struck down the federal authorization for the proposed Cheviot mine. The CRC fails to provide further arguments and evidence related to their case before the time allotted by the court. This results in the calling of a new environmental hearing.
September 1999 Sept. 9: The Joint Panel review of the proposed Cheviot Mine re-opens.
June 1999 The original Joint Panel is reappointed and a supplemental review of the Cheviot Mine application is ordered.
May 1999 CRC appeals the decision of Federal Court to strike down the authorizations. The parent company says it has alternatives, but continues pursuing the Cheviot location.
April 1999 Whitehorse Wildland Park is established, excluding the proposed mine area.

The Sierra Legal Defence Fund and AWA win a lawsuit challenging the adequacy of federal-provincial review of the mine application.

April 8 – AWA Coalition wins the lawsuit. The Federal Court of Canada Trial Division, Federal Justice Douglas R. Campbell strikes down authorizations granted for the Cheviot mine under the Fisheries Act. He deems the Panel review did not meet the requirements of CEAA. He rules that the environmental assessment was incomplete due to deficiencies in assessing cumulative impacts. He rules that the permanent dumping of waste rock on migratory bird habitat contradicts the Migratory Bird Convention Act, which prohibits the deposition of substances harmful to migratory birds. No authorization has since been issued for the Cheviot coal access.

March 1-3, 1999 A Federal Court Hearing proceeds regarding the lawsuit launched by the ENGOs.
December 1998 The AWA Coalition wins the appeal for a new trial regarding the Cheviot Coal Mine development.
August  1998 Aug. 17: The first set of authorizations are issued to CRC by the Minister of Fisheries and Oceans, David Anderson, for the Cheviot Mine Access Corridor which deals with upgrading the existing Grave Flats road. It also includes the building of river and stream crossings and rip-rapping river banks. By granting these authorizations, DFO uses authorizations as a vehicle for imposing mitigation measures to protect fisheries and migratory bird values.
February 1998 Scientists issue a position statement asking Canada to protect the area instead of allowing the proposed mine.
December 1997 The World Heritage Committee asks the Federal Government to reconsider the 1997 approval and work on alternatives with Alberta Government.

UNESCO World Heritage Committee urges Canada to reconsider 1997 mine approval & work on alternatives with Alberta. The Cheviot mine site is to be located only 1.8 km from Jasper National Park, a World Heritage Site.

December 2 – The Federal Court dismisses CRC's and DFO’s motion to strike down the ENGO lawsuit.

October 2, 1997 DFO grants approval for the Cheviot Mine subject to stringent conditions to protect the environment. These mitigation requirements include:
  • A phased development schedule (pit by pit) to collect data and evaluate cumulative effects
  • Federal government participation in 2 committees responsible for Cheviot:
    • Conservation and Reclamation Review Committee (on site environment issues like water, air, fish and wildlife)
    • Northern East Slopes Environmental Resource Committee (off site issues such as wildlife management)

The AWA coalition (CPAWS, JEA, Pembina) and CNF launches (files) a lawsuit against the Federal Minister of Fisheries and Oceans and the Joint Review Panel as the review did not comply with requirements of CEAA. The groups argue that the Panel failed to conduct a proper environmental impact assessment (EIA) which CEAA requires for mine approval. There was failure to properly assess the cumulative impacts of logging and mining already planned in area and other project alternatives such as underground mining vs. open pit mining. Consideration of mine alternatives would decrease environmental impacts of the operation. DFO’s issuing of authorizations would also be contrary to the Migratory Bird Convention Act.

August 1997 The Alberta Government approves the development of the Cheviot Mine. The Federal Government approval is still required. The mine would still need the Department of Fisheries and Oceans (DFO) permit to proceed.
June 1997 June 17: The Joint Panel review presents its final report and advises that approval be given for the development of the Cheviot Mine. The conditions of the approval include the removal of the area of upper Prospect Creek from the development plan and the creation of buffer zones of 1000m (1km) between the Cardinal Divide Natural Area and the mine disturbance. The report identifies significant environmental impacts and makes recommendations for mitigation measures. These impacts include harm and loss to fisheries habitat, harm to migratory bird habitat and nesting sites, loss of habitat for grizzlies, and the potential contamination of McLeod River. Although the joint panel is both federal and provincial, in order for the mine to go through, both the Alberta Provincial Government and the Federal Government are required to grant approval.
April 1997 April 10: The Panel hearings reconvene to consider the report from the consultant hired by joint review panel.
March 1997 March 31: The consultant report is released to hearing participants for review.
February 1997 Feb. 20: The Joint Panel environmental hearings end. The Panel orders a consultant to report on and obtain advice with respect to certain aspects of the Cheviot mine plans.
January 1997 The AWA Coalition (Alberta Wilderness Association, Pembina Institute of Appropriate Development, Canadian Parks and Wilderness Society (CPAWS- Edmonton Chapter), Jasper Environmental Association (JEA), and Mr. Ben Gadd) sends a joint application seeking an adjournment of the Joint panel hearing to a later date citing insufficient time to review documentation. This request is rejected.

Joint Panel Hearings into Cheviot Mine begin in Hinton, AB. AWA prepares a joint submission with Coalition ENGOs. The groups argue that due to the intensive nature of the project and the significance of the area to be impacted, the project must be denied. There is great concern regarding the effect of the mine on wildlife and habitat. The coalition argues that the federal-provincial review panel failed to provide the public with convenient access to all documents and correspondence regarding the project.

The Cheviot Mine hearing is adjourned for a week to allow environmental groups more time to review last minute submissions from other participants (about 760pages).

Hearings reconvene in Hinton and would last approximately 3 or more weeks.
October 1996 Oct. 24: The EUB ratifies the agreement to establish a joint environmental assessment panel with the Canadian Environmental Assessment Agency (CEAA) to review Cheviot Mine (federal / provincial panel).
September 1996 Environmental assessment requires expert knowledge from groups such as Environment Canada, Natural Resources and Department of Health and the public. Based on the results of the assessment, the Minister of DFO decides the interests of the public would be best served by referring this project to the Minster of the environment for a panel review. This requires a joint EUB and CEAA panel. A draft agreement is made for the creation of a joint federal/provincial EUB/CEAA Review Panel for review of the Cheviot project since both agencies are required within the process and there would be no overlap or confusion of jurisdiction over the project.

Cardinal River Coal Ltd. plans on logging and construction in April 1997.

April 1996 CRC releases Cheviot Mine Project application. They file the project application with the Alberta Energy Utilities Board (EUB).
March 1996 Applications for Cheviot Coal Project are submitted by CRC to both provincial and federal governments.
  • The Department of Fisheries and Oceans (DFO) receives CRC's request for an authorization for the harmful alteration, disruption or destruction of fish habitat resulting from work or undertakings associated with the Cheviot mine. Under Canadian Environmental Assessment Act, before taking action that would allow the project to be carried out, the Minster of DFO is required to ensure that an environmental assessment of the proposed project is conducted. DFO, therefore, became a responsible authority under the act and immediately initiated a EIA for the Cheviot mine.
  • The project application requests the issue of authorizations under the Fisheries Act from the government for: 1) the access corridor for road upgrades, 2) the industrial complex for earthworks, discharge of groundwater and processing plant; and 3) the mine pit for construction of open pits including permanent dumping of excavated rocks and road between pits and the plant. These authorizations are required in order to proceed with project.
  • These authorizations trigger a Panel review under CEAA. Authorizations are required when a project is likely to harm fish habitat. Through these Fisheries Act authorizations, the federal government sets out the conditions that CRC must meet to satisfy concerns over fish, fish habitat and migratory birds. Until the Federal Government is satisfied, authorizations will not be granted.
  • DFO consults other federal departments and interest groups and concludes the mine project could result in significant environmental impacts and require a federal provincial review under CEAA.
1994 October – Cardinal River Coal Ltd (CRC) announces plans to develop the Cheviot Mine.
1990 August - The Coal Branch Sub Regional Integrated Resource Plan is approved by the Economic Planning Committee of Alberta Government Cabinet. The proposed mine area is upgraded to Critical Wildlife Zone. Critical wildlife zone is defined as and area “crucial to the maintenance of specific fish and wildlife populations.”
1982 AWA advocates preservation of the Cardinal Divide area and includes it on its Endangered Wilderness map.
1950 Mountain park underground mining operations ceases in 1950 after 39 years when the railway switches to diesel fuel.
1911 Mountain Park coal mining begins on proposed Cheviot Mine site to extract metallurgical coal.
Document Actions